When the COASTAL DRILLER is loaded as shown in the sample load form Number 3 (drilling), the hook load is placed in the pipe racks. What would be the new variable load? |
A) 2,381.0 kips |
B) 3,381.0 kips |
C) 3,658.8 kips |
D) 4,381.0 kips |