The charterer has completed loading the vessel in 3 days instead of the 5 days agreed to in the charter party. As a result of this, the __________. |
A) ship owner may charge for two lay days |
B) charterer may receive dispatch money |
C) stevedore may collect demurrage |
D) consignee may be required to pay a ceaser fee |