You are the operator of a 296 GRT uninspected towing vessel. Its construction was contracted for after August 27, 2003. In addition to the hand portable fire extinguishers, how much other fire extinguishing equipment are you required to have on board?
A) An approved water mist fire protection system and a fixed CO2 fire extinguishing system
B) Both an approved B-V semi-portable fire extinguishing system and an approved water mist fire protection system
C) Either an approved B-V semi-portable fire extinguishing system or a fixed fire extinguishing system
D) Both an approved B-V semi-portable fire extinguishing system and a fixed fire extinguishing system